Facilities Update

The Facilities Department is working closely with contractors to take advantage of the imposed center closures by moving MRR projects that were initially scheduled for later in the year up on the calendar

To comply with the Pima County Health Department guidelines staff is sanitizing all pool decks and pool furniture before every daily session with the Wysiwash Sanitation System.

The active ingredients in Wysiwash has been shown in numerous tests to be effective against:

  • Parvovirus
  • Distemper
  • Coronavirus
  • Giardia
  • Leptospira
  • Listeria
  • Feline Herpesvirus
  • Canine Parvovirus
  • Feline Calicivirus
  • Feline Panleukopenia
  • HIV Virus
  • MRSA
  • Hepatitis Virus
  • Polio
  • E. Coli
  • Salmonella
  • Swine Flu
  • Avian Influenza (Bird Flu)
  • Streptococcus
  • Staphylococcus

Abrego North

  • The access ramp for the Glass Artists Club’s storage shed is being fabricated and install

Abrego South

  • Handrail anchor cups and an automatic pool water leveler may be installed before the center re-opens.

Canoa Hills

  • The court contractor portion of the bocce court project is complete. Additional concrete work will be conducted on the south end of the courts to provide placement of benches and relocation the club’s shed. Staff is awaiting designs and specifications from the club in order to have metal hand rails fabricated
  • The painting of the exterior of the center is complete

Canoa Ranch

  • Resurfacing project or the spa is underway. The contracted portion of this projects is expected to be completed by 6/5. Staff will need several days after the deck work is completed to clean the pool, spa and deck area

Casa Paloma 1

  • Full remodel of the locker rooms and exterior shower is underway
  • LED lighting upgrades in the recreation room will be completed soon
  • Resurfacing project of the spa is underway

Continental Vistas

  • Seal coating of the parking lot has been completed. However, some areas were identified as in need of further repair. Staff is in talks with the contractor to execute these repairs

East Center

  • Installation of additional doors for the fitness room has been completed
  • Replacement of the single pane windows around the center is nearing completion
  • Loss of water below the pool deck has been detected. Leak detection was performed on the circulation piping of the pool and spa. Also, the pool basin was tested for leaks and inspected for structural deficiencies. Leaks were identified at the bottom of the basin. The pool is being drained in order to inspected these areas further. Two preferred pool contractors have been contacted to provide analysis of pool’s structural condition and options for remediation

Las Campanas

  • Repair work to the pool deck has begun. This work includes complete scarifying of the deck surface, reapplication of acrylic lace texture and recoating. The contracted portion of this projects is expected to be completed by 6/12. Staff will need several days after the deck work is completed to clean the pool and spa.

Santa Rita Springs

  • The modernization and upgrades work for the elevator has been completed
  • Crack filling and painting of the bridge walkway is nearing completion. The bridge will reopen for foot traffic early next week

West Center

  • Asphalt repairs and seal coating has been completed

Pickleball Center

  • Additional fence top protectors will be installed next week