Update: 3.17.23
The following projects are currently in-process:
- Desert Hills Fitness. Electrical and Plumbing rough-ins are complete. All intermediate inspections, including insulation inspection performed this morning, have passed. Store front windows and door openings are framed out. Interior framing is complete. Sheet rock has been installed. Estimated completion of construction work is the end of April.
- Future Glass Arts space at Santa Rita Springs. Canyon Building & Design were awarded the construction contract for the project. An onsite preconstruction meeting was conducted on March 14 with the General Contractor, architect, club leadership and staff.
- Expansion of Ceramics at Desert Hills. The Board approved moving forward with having the architect finish developing Construction Documents and cost estimating the project for expanding the current shop’s area by an estimated additional 900 FT² and updating and bringing up-to-code the mechanical and electrical systems for the Kiln Room. Engineers are finalizing designs for mechanical, plumbing and electrical systems.
- Architectural drawings at Del Sol Clubhouse Construction of the upper floor restrooms is underway. Sheet rock install is complete. Flooring and wall tile installations has begun. Billiards and darts play are now available at the center. Foosball is on its way next. Conceptual designs have been prepared by our architect and are under review by staff. Once the conceptual designs are approved, work will begin on construction documents. This is likely a 4-5-week process. Completed construction documents will be submitted to Pima County for review. There is usually a 3-5-week review period by the County before construction permit is issued. RFPs or Invitations to Bid can go out to qualified construction contractors during the County review period.
- Architectural, space, and cost estimates for a potential West Center Arts Center. Programming designs have been developed and received by the architect and are under review. Alternative plans to be considered for expanding WC Lapidary.
- Casa Paloma 1 Center will be closed from Monday, April 24 – Friday, April 28 while the HOA is having asphalt work throughout the neighborhood conducted. The center will reopen on the morning of 4/29.