Project Update 9/22/2023
Future Glass Arts space at Santa Rita Springs.
- The major construction phase is complete.
- Punch list items are currently being addressed.
- Millwork is being fabricated and will be installed as it is completed.
Del Sol Clubhouse and parking lot
- Construction Documents for the lower-level billiards room, upper floor game room and parking lot are nearing completion.
- The design package has been sent in to the Cost Estimator.
- Permitting may be a 10-week period due to the Development Plan of the parking lot.
Canoa Hills Center is closed for remodel work to be conducted.
- We are working toward a mid-October completion of the locker rooms and restrooms.
- Shower and floor drains throughout the locker rooms needed to be water jetted to clear out blockages and to allow for free-flowing drainage.
- This work caused a delay in the floor prep and installation of floor tile
- Before and after inspection of the drain lines have been conducted.
- Water heater replacements are complete.
- HVAC, Plumbing, and both Rest Room tile installation have been completed
- Drywall ceiling and lighting are being installed in the restrooms.
- Wallboard and waterproofing installed in locker rooms and tiling is underway.
- New flooring and paint are being scheduled for the Fitness Room, Auditorium and hallways.
- The pool deck has been resurfaced
- New pool deck furniture has been received.
Architectural, space, and cost estimates for a potential West Center Arts Center.
- Staff met with the architect to review programming notes and provided feedback to continue with the current design.
- Cost estimation work is also underway
Approved Club funding requests for 2023:
Upgrades for the Woodshop vacuum system.
- Construction documents have been completed and have been approved by Pima County.
- The building permit has been issued
- We are seeking proposals from multiple contractors.