Facilities Project Reports

Project Update 9/22/2023

Future Glass Arts space at Santa Rita Springs.

  • The major construction phase is complete.
  • Punch list items are currently being addressed.
  • Millwork is being fabricated and will be installed as it is completed.

Del Sol Clubhouse and parking lot

  • Construction Documents for the lower-level billiards room, upper floor game room and parking lot are nearing completion.
  • The design package has been sent in to the Cost Estimator.
  • Permitting may be a 10-week period due to the Development Plan of the parking lot.

Canoa Hills Center is closed for remodel work to be conducted.

  •  We are working toward a mid-October completion of the locker rooms and restrooms.
  • Shower and floor drains throughout the locker rooms needed to be water jetted to clear out blockages and to allow for free-flowing drainage.
  • This work caused a delay in the floor prep and installation of floor tile
  • Before and after inspection of the drain lines have been conducted.
  • Water heater replacements are complete.
  • HVAC, Plumbing, and both Rest Room tile installation have been completed
  • Drywall ceiling and lighting are being installed in the restrooms.
  • Wallboard and waterproofing installed in locker rooms and tiling is underway.
  • New flooring and paint are being scheduled for the Fitness Room, Auditorium and hallways.
  • The pool deck has been resurfaced
  • New pool deck furniture has been received.

Architectural, space, and cost estimates for a potential West Center Arts Center.

  • Staff met with the architect to review programming notes and provided feedback to continue with the current design.
  • Cost estimation work is also underway

Approved Club funding requests for 2023:

Upgrades for the Woodshop vacuum system.

  • Construction documents have been completed and have been approved by Pima County.
  • The building permit has been issued
  • We are seeking proposals from multiple contractors.